PREPARATION SITE PREPARATION Check the national and local building codes BEFORE installation. GATE Gate must be constructed and installed according to ASTM F2200 standards (refer to page 4). Gate must fit specifications of operator (refer to specifications). CONDUIT & CONCRETE PAD Conduit must be UL approved for low and high voltage. Consider the operator placement BEFORE installing the pad or post. Concrete Pads 10
10
PREPARATION
SITE PREPARATION
Check the national and local building codes
BEFORE
installation.
GATE
CONDUIT & CONCRETE PAD
Gate must be constructed and installed according to ASTM F2200 standards (refer
to page 4). Gate must fit specifications of operator (refer to specifications).
Conduit must be UL approved for low and high voltage. Consider the operator
placement BEFORE installing the pad or post.
Concrete Pads