LiftMaster CSL24UL Installation Manual - Page 10
Step 1 Determine Location for Operator, Standard Installation
View all LiftMaster CSL24UL manuals
Add to My Manuals
Save this manual to your list of manuals |
Page 10 highlights
INSTALLATION Step 1 Determine Location for Operator Check the national and local building codes before installation. Standard Installation 1. The gate operator should be installed near the front roller of the gate. Lay out the concrete pad. 2. Install the electrical conduit. 3. Pour a concrete pad (reinforced concrete is recommended). Rear Installation 1. The gate operator should be installed near the back of the gate in the OPEN position. Lay out the concrete pad. 2. Install the electrical conduit. 3. Pour a concrete pad (reinforced concrete is recommended). 10
10
Step 1 Determine Location for Operator
Check the national and local building codes before installation.
Standard Installation
1.
The gate operator should be installed near the front roller of the gate. Lay out the concrete pad.
2.
Install the electrical conduit.
3.
Pour a concrete pad (reinforced concrete is recommended).
Rear Installation
1.
The gate operator should be installed near the back of the gate in the OPEN position. Lay out the concrete pad.
2.
Install the electrical conduit.
3.
Pour a concrete pad (reinforced concrete is recommended).