HP D2D4009fc HP StoreOnce 6500 Backup Installation Planning and Preparation gu - Page 5

Product configuration, Location, Power/PDU requirements

Page 5 highlights

Product configuration Table 2 Product configuration Ensure that the delivered materials match the Bill of Materials (BoM) and that there is no damage to boxes or components. Purchase information Products Purchased Count Capacity Note any requirements for: • Capacity upgrades and licenses • Replication and Catalyst licenses • Security license • Couplet(s) to be installed • Additional cabling requirements and make sure they are pre-laid Location At the time of placing the order, make sure that there is a suitable location with access to install the product. This must be a data center environment and not an office environment. (See Product specifications (page 12) for more details.) It should conform to the following requirements: 1. The receiving dock, storage area, and receiving area are large enough to allow movement of and access to crated or packed equipment. 2. The floors, elevators, and ramps are able to support the weight of the delivered equipment as it is moved to the installation location. 3. The installation location must provide: • Sufficient space to accommodate the installed product. nl When installing two racks, the units should be located next to each other, to ensure there are no problems with cable lengths. NOTE: Sufficient space, at least 12 inches (30 cm), must be available to the right-hand side of the rack to ensure that there is enough clearance to maneuver the disks in and out of drawer 2. • Appropriate power, air conditioning, cabling, and fire protection. • Adequate protection from electrostatic discharge (ESD). • Adequate protection from electrical/radio frequency interference. • Adequate protection from dust, pollution, and particulate contamination • Adequate acoustic insulation for operating the system. Power/PDU requirements At the time of placing the order, make sure that the location can support the HP StoreOnce Backup System's input power and power outlet requirements. The AC power input for the HP StoreOnce Backup System has a duplex PDU structure, which enables the entire rack to remain powered on if power is removed from one of the two power distribution panels. Prior to installation you should confirm that you have specified the correct PDU for your geographical location and connector type and that you have sufficient power outlets. See Power/PDU requirements (page 12). Product configuration 5

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29

Product configuration
Table 2 Product configuration
Ensure that the delivered materials match the Bill of Materials (BoM) and that there is no damage to
boxes or components.
Purchase information
Capacity
Count
Products Purchased
Note any requirements for:
Capacity upgrades and licenses
Replication and Catalyst licenses
Security license
Couplet(s) to be installed
Additional cabling requirements and make sure they are pre-laid
Location
At the time of placing the order, make sure that there is a suitable location with access to install
the product. This must be a data center environment and not an office environment. (See
Product
specifications (page 12)
for more details.) It should conform to the following requirements:
The receiving dock, storage area, and receiving area are large enough to allow movement of
and access to crated or packed equipment.
1.
The floors, elevators, and ramps are able to support the weight of the delivered equipment as it
is moved to the installation location.
2.
The installation location must provide:
3.
Sufficient space to accommodate the installed product.
nl
When installing two racks, the units should be located next to each other, to ensure there are
no problems with cable lengths.
NOTE:
Sufficient space, at least 12 inches (30 cm), must be available to the right-hand side
of the rack to ensure that there is enough clearance to maneuver the disks in and out of drawer
2.
Appropriate power, air conditioning, cabling, and fire protection.
Adequate protection from electrostatic discharge (ESD).
Adequate protection from electrical/radio frequency interference.
Adequate protection from dust, pollution, and particulate contamination
Adequate acoustic insulation for operating the system.
Power/PDU requirements
At the time of placing the order, make sure that the location can support the HP StoreOnce Backup
System’s input power and power outlet requirements. The AC power input for the HP StoreOnce
Backup System has a duplex PDU structure, which enables the entire rack to remain powered on
if power is removed from one of the two power distribution panels.
Prior to installation you should confirm that you have specified the correct PDU for your geographical
location and connector type and that you have sufficient power outlets. See
Power/PDU
requirements (page 12)
.
Product configuration
5